Q.The sequence that minimizes the total elapsed time required to complete the following jobs is Processing times in hours No. of Jobs: 1 2 3 4 5 6 Machine A: 4 8 3 6 7 5 Machine B: 6 3 7 2 8 4
Correct answer: 3 → 1 → 5 → 6 → 2 → 4